Dear Eng, Majdy.With reference to the above mentioned subject and visiting the site to get the latest updates, show us that the Contractor started masonry work (Block work ) in the first basement floor- Zone 806- without notify us, where should the contractor notify us of any new work and provide start-up paper for any new items, so we can follow-up work from beginning, and based on the project specifications Contractor should build mockups for typical exterior and interior walls for each type of masonry unitsspecified in full dimensions as indicated on Drawings including different types of openings.a. Include head-of-wall joint in interior non-fire rated wall assembly.b. Include head-of-wall joint in interior fire-rated wall assembly.c. Include head-of-wall joint in typical exterior wall assembly.d. Include intersecting walls anchorage.e. Include anchorage to abutting concrete.Note: Approved mockups may become part of the completed Work if undisturbed at time ofSubstantial Completion.