Possession of Site & Contract documents
Contract documents duly signed & stamped and in place
Further to soft start mobilization, we instruct you to take site possession on 3rd January 2016 in accordance with the clause 41 and to carry out the works as per Contract Agreement, Drawings and specifications noting the dates below:
Contract Commencement 3rd January 2016
Contract Period (18 months) 547 Days
Contract Completion 2nd July 2017