10.1 Liquidated Damages
If the contractor fails to comply with the Time for Completion in accordance with Clause 9.1 for the whole of the contract Works or, if applicable, any Section within the relevant time prescribed by Clause 9.1, then the contractor shall pay to the Client the relevant sum stated in the same clause as liquidated damages for such default for every day or part of a day which shall elapse between the relevant Time for Completion and the actual time for completion of the whole of the contract Works or the relevant Section, subject to the applicable limit stated in this contract. The Client may, without prejudice to any other method of recovery, deduct the amount of such damages from any monies due or to become due to the contractor. The payment or reduction of such damages shall not relieve the contractor from his obligation to complete the contract Works, or from any of his obligations and liabilities under the contract.