allowed to obtain Dig permit, submission of MAS, approval of sub contractors, carrying out trials pits to understand existing foundations and services to determine methodology for Enabling works, accessing Demolition & Temporary programmes, etc.
2.0 Possession of Site & Contract documents
2.1 Contract documents duly signed & stamped and in place
2.2 Further to soft start mobilization, we instruct you to take site possession on 3rd January 2016 in accordance with the clause 41 and to carry out the works as per Contract Agreement, Drawings and specifications noting the dates below:
Contract Commencement 3rd January 2016
Contract Period (18 months) 547 Days
Contract Completion 2nd July 2017
3.0 Insurances & Bonds
3.1 We confirm receipt of originals Advance Payment Guarantee Bond, Performance Bond and Contract Insurances