Reference to our engineer visit to Al Bida 132KV OHTL project, they pass by 380KV Tabouk BSP location at Tabouk Al Sharma road. It was observed that time being there is only 380KV OHTL terminal tower is erected along with stringing and we did not find any 132KV OHTL Tower erected in front of 380KV Tabouk BSP area.
As it was bring to the notice of EHV to avoid any hindrances for construction of 380KV OHTLs emanating from Tabouk BSP, it is strongly recommended to advice 380KV OHTL contractor (MEEDCO) to construct 132KV OHTL for Tabouk S/S # 4 in front of dedicated area for 132KV gantry structures to avoid relocation/swapping of 132KV OHTLs during future projects.
In this regard it is required to arrange a meeting at our Jeddah office with EHV Projects Technical Support Division, EHV Projects, 132/110KV Planning Div. and Survey div. to settle the requirements for ongoing as well as future projects.