It’s recommended that after the above mentioned pending meeting on 7th December, SRO with the Consultant should assess if Al-Mobty’s are capable of constructing the project to a reasonable time schedule. Al-Mobty are severely under resourced both with labor and equipment, when compared with the project Histogram.