I successfully minimized the Work Orders in NGID F/L from more than 170 work orders, now it is between 75 – 90 work orders.
I have no work order over 365 days for long time.
I respond for 28 emergency and 15 urgent notifications.
I have prepared all required materials and all heavy equipment for next total shutdown and the maintenance are ready for total shutdown.
I participated in closing 40 work sheet job.
I provided all planning support to tackle 6 plant shutdowns for AWIP, UWIP-1, UWIP-3 and UWIP-4.
I have created ACCESS file to help planners in finding materials easily and faster than using a paper chart and to assist in the calculations to calculate the turnaround time and charging limit for work order.
I have provided two 12” isolation valves for (31,796.66 $) each from Surplus Yard, instead of valve MTL#1000817780 that were by (62,000 $) each.
W.Os#11166034 & 11165238.
I sent 3 defective 12” valves to MSSD shop, 2 of the valves passed and it is usable now. The price of the new valve (62,000 $) MTL#1000817780.
WO# 11196993, 11196997 & 11136482.
I held 99% of the weekly OME meetings regularly.
The planning KPIs in NGID Flow line unit are good.
I submitted 3 innovations, 2 safety suggestions and 2 near misses.
I covered SGID Flow Line and provided all required support for many times during their planner vacation.
I provided all planning support for contractor coordinators for NGID contractor jobs.
I passed 5 E-Learning courses.