With reference to your letter dated 26th July 2015 Ref. No. DS016-P01-JABOR-LET0919 regarding the dewatering works for DS016 Package-I Roads and Infrastructure in Wakrah West, MMUP Phase-2 PKG-14. Above all we would like to appreciate you kind cooperation and patience in this matter. Our intentions are very clear from the beginning to do the enabling works on fast track and start the pumping of water but the delays are inevitable due to the permits for road excavations, directional drilling in Mesaieed Highway and excavation permits for the other side of the road. Without securing the proper documentation and clearance of utilities with the concern authorities/ department we can't touch any road and area. But currently we will make sure the Installation works will complete as per the below mentioned schedule to avoid any more delays in completion of the milestones in due dates.