• Project Challenges:1. Site was consists of random pipe lines.2. The surface layer of soil was sponge layer which did not allow the heavy equipment to move through it.3. No suitable entrances to enter the site and allow equipment to go inside the site, like (Concrete Pumps – Heavy Equipment).• Execution period:1. 84 days to establish full concrete structure.2. 29 days to complete whole finishing work.• Soil research did not show the existence of infantum layers.Sudden and immediate redesign for drilling depth and suitable for foundation