Good day,
Please find below items, FYI & A
UWSP Scaffolding Follow up with Fahad Al-Dossary to update the scaffold and erect new in UWSP before 05/30/2016. Request attached
D/C request Gasket: 22"X 1500 Follow up with maintenance engineer and material man to process D/C request. W.O#11195526 Email attached
Work sheet
PEU/211, 203, 216, 210 Need to review with Rajaie to clear some mistakes as we discussed. Email attached
UWIP-5 PEU 235/2015 & PEU-24/2016 site visit conducted with fabricator
waiting to order materials Email attached
UWIP-4 PEU-132-2016 Need to check the material list with Rajaie to order it. Package attached
UWIP-4 PEU-034-2016 Need to check the material list with Rajaie to order it. Package attached
UWSP QUU-2 DOOR N#11089802 waiting to open work order Email attached
MATERIALS SHIPPING Follow up with cargo to provide urgent trucks Email attached
Thanks.